ON SITE 869 SHORING

On Site: 869 Shoring

The completion of the Soil Nail wall shoring wall for the 869 project was completed in mid-August 2023. Condon Johnson Associates, Mac Brown Excavating and Caputo Construction worked together to install the specialty shoring system called a soil nail wall. This shoring system uses special soil nails or tie-backs that are drilled and grouted in the hillside to support a 6” thick shotcrete shoring wall system. This wall will allow construction of the main residence and the installation of the concrete retaining walls.